Shipyard
article | Reading time7 min
Shipyard
article | Reading time7 min
Since its construction in the 14th century, the Tour Saint-Nicolas has been a colossus with feet of clay. Today, works of exceptional technical complexity and unprecedented scale are being carried out to secure and stabilise the structure for the long term.
Built between 1332 and 1374, the Tour Saint-Nicolas, together with the Tour de la Chaîne, forms the gateway to La Rochelle’s Old Port.
The building was constructed on marshy ground reclaimed from the sea. Its foundations rest on 6-metre-high oak piles. These piles, which are almost touching one another, are connected by a floor of beams. On top of this wooden foundation slab sits a masonry foundation slab approximately 5 metres high. The tower’s foundations rest on these elements.
However, on this unstable ground, due to its own weight and certainly as a result of a major climatic event in the 14th century, the tower sank by more than 20 cm on one side whilst it was being built.
Its foundations were then widened and reinforced, and a buttress tower was added. The building was stabilised, but its silhouette remains leaning towards the east, earning it the nickname the ‘French Tower of Pisa’.
Over the centuries, and following various alterations to the tower and its immediate surroundings, these weaknesses have become more pronounced. Cracks have appeared and worsened, posing an even greater threat to the tower’s structure.
The Tour Saint-Nicolas: an urban keep or the ‘French Tower of Pisa’?
© Patrick Tournebœuf – Tendance Floue – Monuments Nationaux
The worsening of the cracks led the Centre des monuments nationaux to place the Tour Saint-Nicolas under monitoring from 2019.
A multidisciplinary team, comprising the chief architect for historic monuments, Philippe Villeneuve, structural engineers and geotechnical engineers, was therefore mobilised to identify the factors affecting the tower’s stability.
Several techniques are being used to monitor the existing cracks and the movement of the building as a whole.
The data collected has revealed that the tower is tilting towards the north-east, as well as a steady displacement of a few millimetres per year.
© Patrick Tournebœuf – Tendance Floue – National Monuments
In July 2024, the Tour Saint-Nicolas was evacuated following an alert triggered by a sensor. The alert, which ultimately proved to be a false alarm, enabled the detection of unusual movements in the tower.
Analysis of the data revealed, in particular, a displacement of 15 to 20 mm over a short period, and a difference in deformation between the upper and lower parts of the tower.
These observations led the teams responsible for monitoring the tower to adapt their monitoring tools in order to better understand these changes and identify their causes.
© Patrick Tournebœuf – Tendance Floue – Monuments Nationaux
In May 2025, the Centre des monuments nationaux began emergency consolidation works to restore the tower’s monolithic structure.
This project, led by Olivier Salmon, Chief Architect for Historic Monuments, involved the installation of ring beams in the upper part of the building and a metal brace in the lower part.
Tie rods were also installed inside the tower to prevent the spur and the north-west turret from shifting, by anchoring them to the rest of the building.
This first phase of works was completed at the end of 2026.
© Patrick Tournebœuf – Tendance Floue – National Monuments
The chief architect’s studies for permanent stabilisation are currently underway.
© Patrick Tournebœuf – Tendance Floue – Monuments Nationaux
© Patrick Tournebœuf – Tendance Floue – Monuments Nationaux
© Patrick Tournebœuf – Tendance Floue – Monuments Nationaux
© Patrick Tournebœuf – Tendance Floue – National Monuments
© Patrick Tournebœuf – Tendance Floue – Monuments Nationaux
© Patrick Tournebœuf – Tendance Floue – National Monuments
© Patrick Tournebœuf – Tendance Floue – National Monuments